Updated: 11 November 2026
Construction disputes in the UAE commonly arise over project delay, unpaid contractor entitlements, variations and additional works, defective or non-compliant work, performance security, and termination. Proving that a project was late or that an invoice remains unpaid is rarely enough on its own. The outcome usually depends on the contract, approved programme, notices, payment certificates, site records, authority of the person issuing instructions, and the causal link between each event and the time or money claimed.
Federal Decree-Law No. 25 of 2025 promulgating the new Civil Transactions Law became effective on 1 June 2026. The UAE Government’s official Civil Transactions Law announcement confirms that the provisions governing contracts for works were modernised, including contractor duties, defective materials, obstacles to performance, correction of works, engagement of another contractor, exceptional circumstances affecting contractual equilibrium, and termination before completion.
A practical construction-claim strategy begins by preserving the project record, building a detailed chronology, analysing the contract and programme, and separating time claims from money claims. The party can then decide whether the objective is payment recovery, an extension of time, defence against delay damages, rectification of defects, termination, or a negotiated solution that allows the project to continue.
Construction disputes include claims arising from building, infrastructure, fit-out, maintenance, engineering, specialist works, and related project contracts. A dispute may arise between an employer and main contractor, a main contractor and subcontractor, or involve a consultant, supplier, designer, or other project participant depending on the contractual chain and each party’s role.
A project may be governed by a main agreement together with general and particular conditions, specifications, drawings, bills of quantities, programmes, addenda, and variation orders. Those documents do not always have the same priority if they conflict. The starting point is therefore to identify the full contract documents and their order of precedence, then connect each claim to the clause that governs it.
The governing law, project location, agreed court or arbitral forum, contract language, and any mandatory pre-dispute steps must also be reviewed. Government contracts, projects in financial free zones, and contracts subject to special local regulation may require separate analysis.
The official UAE legislation platform explains that the new Civil Transactions Law modernised the rules governing contracts for works. The official legislative announcement highlights updated rules on contractor responsibility for materials supplied by the employer, immediate notice of defects or obstacles, performance within the agreed or reasonable period, correction of defective work, employer rights to rescission or replacement performance, and unforeseen circumstances affecting contractual equilibrium.
The new framework also addresses exceptional general circumstances that were not reasonably foreseeable at the time of contracting and that fundamentally disturb the financial balance of a construction contract. Depending on the case, a court may restore balance through an extension of time, adjustment of remuneration, or rescission. This does not mean that every increase in cost or difficulty of performance automatically creates a compensation claim. The event, lack of foreseeability, and actual impact on the contract still have to be proven.
The law also regulates the employer’s ability to bring the works contract to an end before completion, while taking account of contractor expenses, the value of completed work, lost profit, and any savings or gains resulting from the stoppage. This route should not be confused with termination for contractor breach, because the legal basis and financial consequences are different.
Electronic correspondence, project records, and expert evidence are also affected by the UAE Law of Evidence in Civil and Commercial Transactions. Court proceedings are governed by the Civil Procedure Code, while a valid arbitration clause must be assessed under the federal Arbitration Law before substantive court proceedings are started.
Important: the date of the contract and the date of the disputed events matter. The 2026 Civil Transactions Law should not be assumed to apply automatically to every older contract or earlier event. Transitional rules, governing-law clauses, and special legislation must be checked.
| Dispute Issue | Documents That Usually Matter Most |
|---|---|
| Delay / extension of time | Baseline and updated programmes, progress reports, delay notices, meeting minutes, site instructions, and critical-path analysis. |
| Payments / interim certificates | Contract, payment schedule, applications, consultant certificates, invoices, account statements, proof of progress, and objections. |
| Variations / additional works | Variation request, instruction, price and time approval, revised drawings, labour records, equipment records, and material records. |
| Defects / non-compliance | Specifications, inspection requests, test reports, site photographs, expert reports, rectification correspondence, and handover records. |
| Termination / taking over works | Termination clause, notices, cure periods, condition surveys, completion cost records, and breach history. |
| Bonds / retention | Bond wording, call requirements, completion certificate, handover records, release conditions, and alleged set-off. |
The contractual completion date alone does not determine responsibility for delay. A proper analysis asks whether the relevant event affected a critical activity and therefore delayed project completion, who caused the event, whether the required notice was issued on time and in the agreed form, and whether concurrent causes or later programme changes affected the result.
Delay may be attributed to the contractor where there are inadequate resources, procurement delays for risks allocated to the contractor, poor coordination, rework of defective work, or failure to follow the programme without a contractual excuse. Depending on the contract and severity of the breach, consequences can include delay damages, additional completion costs, formal notices, or termination.
However, a delay-damages figure should not simply be inserted into the final account. The clause, cap, calculation period, partial performance, employer contribution, and applicable rules on agreed compensation must be reviewed.
Employer-side delay may arise from late site access, delayed drawings or approvals, repeated design changes, restricted access, delayed material approvals, or non-payment that affects progress. A contractor should establish the event, date, contractual responsibility, and actual impact on the programme rather than relying on a general statement that the employer caused delay.
An extension-of-time claim should follow the contract and identify the delay event, affected period, critical activity, contractual entitlement, notice compliance, and mitigation steps. Where the contract imposes strict notice or particulars deadlines, late submission can create arguments about loss of contractual entitlement or make the claim harder to prove.
Concurrent delay arises where different causes overlap and each may affect the completion date. There is no automatic legal outcome merely because both sides use the word ‘concurrent’. The contract, programme logic, factual sequence, and actual impact of each event must be analysed to determine the consequences for time, prolongation costs, and delay damages.
A payment claim should start by identifying the legal and contractual basis of each amount. The claim may concern an approved interim certificate, completed but uncertified work, variations, materials on site, prolongation costs, retention release, or the final account. Each category requires different evidence and may have different contractual conditions.
A consultant’s certificate can have significant contractual weight, but it does not necessarily replace analysis of the agreement and facts. Depending on the contract, certificates may be challenged where there is error, lack of authority, incorrect measurement, or non-compliance. The objection period, certification procedure, and distinction between valuation and payment due date should be reviewed.
Many UAE construction contracts deduct a percentage from interim payments until specified milestones such as taking-over or expiry of the defects-liability period. The parties should identify the contractual trigger for release of each portion, any outstanding defects, permitted set-off, and the certificates required before release.
The final account can become a separate dispute where one party adds deductions, delay damages, completion costs, or disputed variations. Earlier claims, responses, agreed interim settlements, and any final-release wording must be reviewed carefully. A signed waiver or acceptance of payment as ‘full and final settlement’ may affect remaining claims depending on its wording and circumstances.
A variation may add or omit work, alter design, sequencing, materials, quantities, or methods of performance. The contractor’s entitlement to additional time or payment depends on the contract, authority of the person giving the instruction, compliance with notice and valuation procedures, and proof that the work falls outside the original scope.
Where a contractor proceeds on an oral instruction or an email from someone who lacks contractual authority, a dispute may arise over whether a valid variation existed and how it should be valued. Instructions should be confirmed promptly, a written variation requested, the price and time impact submitted, and separate records kept for labour, plant, and materials.
The absence of an agreed price does not necessarily mean the work is free, but carrying out extra work does not automatically entitle the contractor to any amount it chooses. Contract rates, valuation mechanisms, expert evidence, and surrounding facts may all become relevant.
A dispute should distinguish between a defect that can be corrected during execution, a defect identified at handover, a latent defect appearing later, and a serious structural defect that affects stability or safety. Responsibility may arise from workmanship, design, materials, employer instructions, misuse, or inadequate maintenance.
A contract may allow the employer to require correction within a reasonable period and, if the contractor fails to act in accordance with the agreed procedure, engage another contractor and seek the cost. Deducting the full rectification cost without proper notice or proof of necessity and reasonableness can itself become disputed.
Decennial liability may arise in relation to total or partial collapse or serious defects threatening the stability or safety of a structure where the statutory conditions are satisfied. It is distinct from the contractual defects-liability period and does not automatically disappear when the contractual maintenance period ends.
The roles of the contractor, engineer, designer, and other parties, the date of handover, nature of the defect, cause of the damage, and type of structure must be examined. Not every crack or operational problem is a decennial-liability case. Technical expert evidence is usually central to identifying the seriousness, cause, and required scope of repair.
Where the employer supplies materials, the contractor must generally protect and use them in accordance with professional practice and the contract, and return unused materials where required. Responsibility for loss, damage, or deterioration can depend on the cause.
If supplied materials are defective or other factors prevent proper performance, the contractor should issue a clear and prompt notice identifying the problem, its effect, and the decision required. Continuing with obviously defective materials without reservation can weaken the contractor’s position. Equally, an employer that supplies late materials or information cannot automatically place all resulting delay on the contractor.
Termination is one of the highest-risk steps in a construction project. It is important to distinguish termination for breach, termination for the employer’s convenience or withdrawal before completion, judicial rescission, and automatic termination due to impossibility. Each route has different requirements and financial consequences.
Before termination, review the alleged breach, termination wording, notice requirements, cure period, method of service, and any precondition such as an engineer’s determination or dispute-board step. The party seeking termination should also confirm that it has complied with its own material obligations.
Wrongful termination can itself become a breach and generate a damages claim. For the wider UAE contract framework, see the related English article on contract termination under UAE law.
After termination, the parties should document the condition of the site, completed work, materials, plant, documents, temporary works, defects, and percentage completion. Site security, ownership or use rights over drawings and data, and the cost of completion should be documented through contemporaneous records, quotations, invoices, and measurable evidence.
Common project security includes performance bonds, advance-payment guarantees, retention guarantees, and other bank instruments. The bond wording must be reviewed separately from the underlying construction contract because the conditions for a call, expiry date, and documentary requirements may differ.
A threatened bond call may require urgent legal assessment, but the existence of an underlying dispute does not automatically stop payment. The nature of the security, wording of the demand, competent forum, and legal conditions for interim measures should be examined promptly. Parties should avoid submitting inaccurate information to the bank, court, or arbitral tribunal.
The main contract and subcontract should be analysed separately. A subcontractor’s rights against the main contractor arise primarily from their subcontract and do not automatically include every right in the main contract unless properly incorporated. Employer approval of a subcontractor does not necessarily create a direct contractual relationship with the employer.
Payment provisions, any pay-when-paid mechanism, variations, programme obligations, suspension rights, termination, security, and proof of delivery or performance should be reviewed. A subcontractor may have a valid payment claim even if it was not responsible for overall project delay.
A strong construction case is not simply a large collection of documents. The better approach is a claim register linking each event to the contractual entitlement, required notice, supporting evidence, time or cost impact, and mitigation. Original emails, programme files, metadata, and contemporaneous records should be preserved rather than edited after a dispute has begun.
| Claim Element | What Must Be Established |
|---|---|
| Contractual entitlement | The clause giving the right to time, money, relief, or damages, and the contractual steps required to preserve that right. |
| Event | When it occurred, who instructed it, what happened on site, and the contemporaneous records. |
| Causation | How the event actually caused the delay, cost, or defect rather than simply occurring during the same period. |
| Quantum | Calculation method, invoices, labour hours, quantities, rates, deductions, and amounts already paid. |
| Mitigation | Reasonable steps taken to reduce delay or cost and the alternatives or quotations considered. |
| Notice compliance | Date, recipient, method of service, contents of the notice, and any response. |
The approved baseline programme, all updates, recovery programmes, and native source files should be retained – not only printed or PDF copies. A delay expert may need the activity logic, relationships, actual progress, and contemporaneous updates to test whether the event affected the critical path.
Useful records can include daily reports, manpower and equipment logs, meeting minutes, inspection requests, delivery records, dated photographs, relevant weather and safety records, and approval correspondence. These records are generally more persuasive when they were created at the time of the event rather than reconstructed after the dispute.
A court or arbitral tribunal may appoint or receive evidence from engineering, delay, or accounting experts. The legal team should present an organised file that explains the expert’s task, the technical issues, and the calculations, and should respond to expert findings within procedural deadlines. Expert evidence assists the decision-maker but does not replace missing contract documents, notices, or project records.
The contract often defines the dispute-resolution route. It may require negotiation, an engineer’s determination, a dispute board, mediation, or another step before court or arbitration. The parties should check whether those steps are mandatory, the deadlines, and the consequence of non-compliance.
If the agreement contains a valid arbitration clause, the parties should analyse its scope, covered parties, seat, institution, rules, language, and number of arbitrators under the UAE Federal Arbitration Law. This is particularly important in multi-contract projects because the main-contract arbitration clause does not automatically bind every subcontractor, supplier, or guarantor.
If court proceedings are appropriate, the competent court, claim value, remedies, evidentiary requirements, and legal translation of foreign-language documents should be addressed. Interim or precautionary applications may be separate from the final determination of the construction claim.
Preserve the complete contract, addenda, drawings, programmes, correspondence, financial records, and native project files. Suspend automatic deletion where appropriate and identify devices, accounts, or systems containing important evidence.
Identify document priority, notice clauses, payment rules, variation procedures, time obligations, termination provisions, security, and dispute-resolution steps. Avoid admissions or waivers before understanding their contractual effect.
Arrange project events from commencement onward and link each event to the corresponding correspondence, programme update, certificate, and decision. A chronology exposes gaps and inconsistencies before they become central in expert or legal proceedings.
An extension of time does not always create entitlement to every prolongation cost. A contractor may have a valuation claim for a variation without a time claim, or a defence against delay damages without a separate monetary entitlement. Each head of claim should have its own legal basis, evidence, and calculation.
Do not automatically suspend work or payment simply because a dispute exists. Review the contractual right to suspend, notice requirements, site-safety consequences, and risk of turning the suspension into a breach. Where the undisputed part can continue without prejudicing legal rights, document the position carefully.
A staged settlement may release an interim payment, agree an extension of time, resolve a variation, or permit the project to continue. Any settlement should define its scope, identify which claims are reserved, and explain the effect on the final account, security, and future claims.
Bin Nakhira & Partners provides Construction Litigation services for employers, developers, main contractors, subcontractors, consultants, suppliers, and other project stakeholders. The review begins with the contract, jurisdiction, chronology, programme, payment records, notices, and project evidence to identify the strongest provable claims and the main legal and commercial risks.
The firm’s work can include preparing or reviewing claims, responses, notices, settlement terms, and dispute strategies; coordinating with engineering, delay, and quantum experts; and representing clients in negotiation, mediation, arbitration, or litigation depending on the contract and facts.
If your project is facing delay, withheld payments, disputed variations, defects, a bond call, or threatened termination, you can request a legal consultation before taking a step that may be difficult to reverse.
Collect the full contract documents, approved programme, notices, payment records, site minutes, and key correspondence. Build a chronology and identify the contractual basis and evidence for each head of claim before focusing on the total amount.
No. Entitlement depends on the contract, cause of delay, impact on completion, notice compliance, programme evidence, and any concurrent delay. Entitlement to additional time is also different from entitlement to prolongation costs.
It depends on the contract, delay cause, calculation period, cap, partial performance, employer contribution, and applicable law. Agreed compensation can also be subject to legal controls in the circumstances provided by law.
A claim may still be arguable depending on the contract, authority of the person giving the instruction, evidence of the additional scope, acceptance of the work, and valuation mechanism. However, failure to follow written variation procedures can make the claim significantly harder to prove.
No. Its effect depends on the contract, the consultant's authority, and any contractual objection procedure. A certificate can be important evidence without necessarily being immune from review in cases of error, non-compliance, or excess of authority.
Termination or rescission may be available where the contract or law permits it and the required notice, cure period, and procedural steps are satisfied. Termination for breach should be distinguished from an employer's withdrawal or termination for convenience before completion.
The defects-liability period is a contractual mechanism for correcting defects during a specified period. Decennial liability is a separate statutory regime that may apply to collapse or serious structural defects threatening stability or safety when its legal conditions are met.
Suspension should not be automatic. The contractor should review the contract, notice provisions, disputed amounts, site safety, and the legal basis for suspension because an unjustified stoppage may itself amount to breach.
Arbitration is mandatory where a valid arbitration agreement covers the relevant parties and dispute. Any mandatory pre-arbitration steps, such as negotiation, engineer determination, or dispute-board procedure, should also be reviewed.
Not automatically. The contract date, disputed event, transitional rules, governing law, and any special legislation must be considered. A claim filed after 1 June 2026 does not by itself mean the new law governs every earlier contractual event.
Legal Notice: This article provides general information only and does not replace legal advice based on the project contract, correspondence, programme, competent jurisdiction, governing law, special legislation, and evidence. The outcome of a construction dispute depends on the specific facts, contractual wording, and proof.
Content updated: 11 November 2026

Managing Partner
Former Chief Justice of the Federal Supreme Court
Abu Dhabi: 2nd Floor, SJ Tower, 18th Street, Abu Dhabi.
Dubai: Office 1610, 16th Floor, Iris Bay Tower, Business Bay, Al Mustaqbal St.
Mail: [email protected]
Mon – Fri: 8.00am – 18.00pm / Sat & Sunday : Closed