Not every delay, breach, or failure automatically gives a party the right to terminate a contract in the UAE. The first step is to identify the law governing the agreement, the nature of the obligation, whether the breach is sufficiently serious, whether the contract contains an express termination or rescission clause, and whether the required notice or cure period has been followed.
Federal Decree-Law No. 25 of 2025 promulgating the new Civil Transactions Law took effect on 1 June 2026. The UAE Government's official announcement of the new Civil Transactions Law confirms the new legislative framework. Articles 234 to 237 regulate key aspects of rescission of bilateral contracts, agreed rescission, force majeure, and the consequences of rescission or automatic termination.
In a typical bilateral contract, the non-defaulting party may, after giving the required notice to perform, seek specific performance or rescission. Compensation may also be awarded where the legal requirements are met. The court retains discretion: it may allow additional time for performance, and it may refuse rescission where the breach has been cured or the unperformed part is minor compared with the contract as a whole.
For that reason, the correct strategy begins with the contract, the evidence, the notice provisions, and a properly calculated claim – not with a short message saying the contract is 'cancelled'. A wrongful termination can itself amount to a breach and create liability for the party that issued it.
The UAE issued a new federal Civil Transactions Law under Federal Decree-Law No. 25 of 2025, effective from 1 June 2026. The official UAE legislation platform provides an English summary of the new Civil Transactions Law.
The law sets out general rules governing obligations and contracts within its scope, but it does not operate in isolation in every dispute. Special legislation may apply to employment, tenancy, insurance, construction, real estate, commercial transactions, government contracts, and other regulated relationships.
The date of the contract and the date of the disputed event must also be checked. Contracts or events that arose before 1 June 2026 may engage transitional rules or the previous legal regime. The fact that a claim is filed after 1 June 2026 does not automatically mean that every provision of the new law applies.
The parties should also review the governing-law clause, place of performance, legal status of the parties, and any court-jurisdiction or arbitration clause. Agreements connected with the DIFC or ADGM may raise separate legal and jurisdictional issues that require independent analysis.
In practical terms, rescission is the dissolution of a valid and binding contract because one party has failed to perform an obligation in a manner that legally justifies ending the contractual relationship. Depending on the circumstances, rescission may arise through a court judgment, a valid agreement between the parties, a statutory rule, or an enforceable contractual provision.
It is important not to confuse rescission with other legal concepts:
| Term | General Practical Meaning |
|---|---|
| Rescission | Ending a valid contract because of non-performance or another ground recognised by law or agreement. |
| Termination | A broader expression that can include bringing an ongoing contract to an end for the future under a clause, statute, or agreement. |
| Automatic termination | The contract comes to an end by operation of law in circumstances such as total impossibility caused by force majeure. |
| Nullity | The transaction fails to produce legal effect because of a defect affecting its formation or legality, depending on the case. |
| Voidability | A contract may be set aside because of a defect affecting consent, capacity, or another legally recognised ground. |
| Mutual cancellation | The parties agree to end the contract and regulate the consequences between them. |
Choosing the correct legal characterization matters because the requirements, consequences, limitation issues, and available compensation can differ. A breach of performance does not automatically make the contract void, and a defect in consent is not always addressed through a rescission claim.
Article 234 of the new Civil Transactions Law addresses rescission in bilateral contracts. In practice, a claim usually requires careful review of the following elements.
The agreement should create reciprocal obligations. A supplier may be required to deliver goods in return for payment; a service provider may be required to perform agreed services in return for fees.
If the dispute concerns whether the contract was valid from the outset, a different remedy such as nullity or voidability may be more appropriate than rescission for non-performance.
The obligation relied upon should normally have fallen due unless the law or the agreement permits action before the due date. Review delivery schedules, milestone dates, prior approvals, extensions, variations, and any conditions precedent.
A breach may take the form of complete non-performance, defective performance, delay, or partial performance. A general allegation such as 'poor performance' is usually insufficient. The obligation, contractual clause, deadline, and actual conduct should be identified precisely.
As a general principle, a demand or notice to perform should precede a request for rescission unless a valid legal or contractual exception applies. The notice should clearly identify the required performance, provide the applicable cure period, and be delivered in the agreed manner with evidence of receipt.
The court may examine the conduct of both parties. If the party seeking rescission is itself in default of a reciprocal obligation, or prevented the other party from performing, that can weaken the claim or change the allocation of responsibility.
The court may refuse rescission if the unperformed part is minor in relation to the contract as a whole, or if the debtor cures the breach through performance. It is therefore important to explain how the breach affected the commercial purpose of the agreement rather than simply proving that some deviation occurred.
The court is not limited to a simple choice between granting and refusing rescission. Depending on the circumstances and the applicable provision, it may order performance, allow additional time, grant rescission, or refuse rescission where the statutory conditions for refusal are met.
Compensation may also be awarded where there is a legal basis for it. A rescission judgment does not automatically prove every amount claimed as damages. The claimant must establish the loss, its connection with the breach, and the calculation of the amount sought.
Before starting proceedings, the party should decide what outcome is actually useful. If receiving the goods, service, or performance remains possible and commercially valuable, specific performance may be the primary objective. If the breach has defeated the purpose of the agreement or made continuation impractical, rescission may be more appropriate.
Claims may sometimes be pleaded on a primary and alternative basis, subject to the applicable procedural rules. However, inconsistent outcomes should not be pursued without a legally coherent structure – for example, treating the contract as fully continuing while simultaneously treating all of its effects as having disappeared.
Article 235 allows parties to agree that the contract will be rescinded automatically if an obligation is not performed, without a judgment creating the rescission. However, a general clause giving a party a right to terminate is not necessarily the same as an automatic-rescission clause.
Review:
Under Article 235, an automatic-rescission clause does not, as a general rule, remove the requirement for notice unless the parties expressly agreed to dispense with it. An otherwise valid termination may therefore fail if the contractual and legal notice steps are not followed.
A party does not normally acquire a unilateral right to end a binding agreement simply because the contract is no longer commercially attractive. A clear contractual or legal right, the other party's agreement, or a court decision may be required.
A contract may provide for termination without cause, termination for specified events, repeated breach, insolvency, or loss of a required licence. Each right must be exercised in accordance with its conditions, including notice periods, fees, settlement of work performed, return of property, transfer of data, and post-termination obligations.
If a party terminates without a legal basis or before completing the required procedure, that party may itself be in breach. Commercial desire to exit should therefore be separated from the legal right to terminate.
A notice to perform documents that the defaulting party was required to remedy the breach and was given the opportunity required by law or contract. It also defines the breach, the payment or performance demanded, and the deadline.
A well-prepared notice should usually identify:
There is no single cure period that applies to every contract. The agreement may specify a number of days, or the nature of the obligation may require a reasonable period. The agreed service method must also be checked because sending a notice to an unapproved email or address can create a dispute over whether notice was validly received.
Article 236 addresses force majeure in bilateral contracts. Where force majeure makes performance totally impossible, the corresponding obligations may be extinguished and the contract may terminate automatically. Partial or temporary impossibility can have different consequences and may involve partial extinction, adjustment, suspension, or a right to seek rescission depending on the facts and applicable rules.
Higher cost or commercial difficulty alone does not automatically establish force majeure. The event, foreseeability, ability to prevent or overcome it, causal connection with the impossibility, and any contractual notice requirements must be analysed.
Force majeure is generally connected with impossibility of performance. Exceptional general circumstances concern situations where performance remains possible but becomes excessively burdensome and threatens the debtor with serious loss.
Article 224 of the new Civil Transactions Law addresses exceptional general circumstances and gives the court, after balancing the interests of the parties, power to reduce an onerous obligation to a reasonable level or order rescission. A party should not simply assume that difficult conditions allow permanent suspension of performance without analysing the legal provision, contract, evidence, and appropriate judicial route.
Construction contracts may also contain special statutory rules concerning contractual balance, variations, delay, and unforeseen circumstances. Those provisions should be reviewed together with the general rules.
Article 237 provides that, when a contract is rescinded or terminates by operation of law, the parties are generally restored to their pre-contract position. If restoration is impossible, compensation may be awarded.
Practical settlement of the consequences may include:
Restoration does not always mean that every payment is simply returned in full. Work may have been completed, a benefit may have been received, damage may have occurred, set-off may apply, and certain provisions – such as confidentiality and dispute-resolution clauses – may be intended to survive termination.
Compensation may be awarded where its legal requirements are satisfied, but it is not automatic in every rescission. The claimant generally needs to prove the breach, the loss, the causal connection, and the amount claimed through a clear calculation supported by evidence.
Where neither the law nor the contract fixes the amount, Article 339 allows the court to assess compensation by reference to actual loss. Depending on the facts, a claim may include the reasonable cost of replacement performance, direct loss, expenses caused by the breach, or amounts contractually due.
The injured party should also take reasonable steps to mitigate loss. A party should not allow avoidable damage to increase and then seek to recover the entire increase from the other side.
Article 340 allows parties to agree in advance on compensation in the contract or in a later agreement, while preserving the court's authority under the legal rules that govern agreed damages.
Important questions include:
A large number written into a contract does not guarantee that the full amount will be awarded, just as a party cannot simply assert that the loss was lower without supporting calculations and documents.
| Issue | Evidence Commonly Required |
|---|---|
| Contract and terms | Signed contract, schedules, amendments, purchase orders, and general terms. |
| Due date | Performance schedule, approvals, completion certificates, and extensions. |
| Breach | Correspondence, reports, meeting minutes, invoices, delivery and acceptance records. |
| Notice | Formal demand, proof of sending and receipt, response, and cure period. |
| Claimant's performance | Payment records, deliveries, approvals, and evidence of readiness to perform. |
| Loss | Invoices, replacement contract, account statements, expert report, and detailed calculation. |
| Mitigation | Alternative quotations, corrective attempts, and steps taken to protect the project or goods. |
| Jurisdiction | Court or arbitration clause, governing law, seat, and party details. |
Review specifications, delivery dates, inspection and acceptance procedures, transfer of risk, defects, and any right to reject or replace goods. Partial performance or acceptance of later deliveries may affect the available remedy.
Identify performance standards, service levels, duration, termination rights, commissions, data, and customer responsibilities. The parties should also address work completed up to termination and the handover of files, systems, and records.
Construction contracts can be subject to special provisions on notice, default, completion, defects, exceptional circumstances, subcontracting, and termination of works. The general rules should not be applied without also reviewing the provisions specific to construction and the detailed contractual terms.
Tenancy agreements can be governed by local legislation and procedures that vary by emirate and property type. A tenancy dispute should therefore be assessed under the relevant rental framework rather than under general contract rules alone.
Employment termination, notice, final entitlements, and related rights are governed by UAE labour legislation. General civil-contract rescission rules should not be applied in isolation from the applicable labour framework.
Government contracts may contain special procedures, approvals, claims mechanisms, and jurisdiction provisions. The contract, contracting authority, tender rules, and any governing legislation or regulations should be reviewed.
Do not read the termination clause alone. Review definitions, obligations, deadlines, notice provisions, variations, force majeure, damages, limitation of liability, governing law, and dispute-resolution clauses.
Arrange the contract date, amendments, performance, payments, correspondence, breach, and notices in order. A chronology can reveal a waiver, extension, acceptance, or course of dealing that may affect the termination right.
Decide whether the objective is performance, exit from the agreement, repayment, compensation, or a legally structured combination of primary and alternative remedies.
Break the amount into clear components and connect each one to a document and contractual or legal basis. Avoid a single unexplained lump-sum demand.
Confirm whether the agreement requires negotiation, mediation, or arbitration before proceedings. Identify the competent court or arbitral seat, the language, and the governing law.
Do not automatically stop your own obligations merely because the other party is accused of breach. The right to withhold performance or suspend obligations should be assessed under the contract and applicable law. An unjustified suspension can turn the party seeking rescission into a defaulting party.
If a valid arbitration clause covers the dispute, arbitration may be the mandatory forum instead of the courts. The federal framework is set out in Federal Law No. 6 of 2018 Concerning Arbitration, subject to applicable amendments and any institutional rules chosen by the parties.
Review the scope of the clause, seat, arbitral institution, number of arbitrators, language, pre-arbitration steps, and availability of interim measures. An arbitration clause may remain effective for disputes concerning the termination and consequences of the contract even after the main contract has ended.
The route depends on jurisdiction, claim value, contract type, and the dispute-resolution clause. Court proceedings are governed by the UAE Civil Procedure Code, while evidentiary issues are also governed by the Law of Evidence in Civil and Commercial Transactions and any applicable special rules.
The file will usually need a statement setting out the contract, breach, notice, and relief sought, together with certified legal translations where required, a detailed claim calculation, and organised evidence. A court may appoint an expert on technical or accounting matters, but expert evidence cannot replace missing core contractual documents.
A supplier agrees to deliver equipment to a company in three batches on specified dates. The first batch arrives late and is alleged to be non-compliant, while the second batch is not delivered despite correspondence. The buyer sends a short termination notice and purchases replacement equipment at a higher price.
The buyer's position cannot be assessed from the delay alone. The review should cover the acceptance specifications, effect of accepting the first delivery, contractual cure period, notice method, whether the delay or defect was material enough to justify rescission, and whether the replacement purchase was reasonable and supported by quotations and invoices.
The buyer may have a valid rescission and damages claim, or it may be found that the termination notice failed to satisfy the agreed procedure, or that part of the loss claimed was not sufficiently connected to the breach. The result depends on the contract and evidence.
Bin Nakhira & Partners provides corporate litigation services for commercial contract disputes, including breach analysis, formal notices, claims for specific performance or rescission, and compensation claims.
The review begins by identifying the applicable law and jurisdiction, then analysing the contract, chronology, evidence, and calculation of the claim. Depending on the agreement and facts, the work may involve negotiation, mediation, arbitration, or representation before the competent court.
If you are considering terminating a contract, have received a termination notice, or are facing a breach-of-contract dispute, you can request a legal consultation before stopping performance, signing a settlement, or starting proceedings.
Not always. The contract wording, notice requirements, seriousness of the breach, and applicable law must be reviewed. Depending on the case, the remedy may be performance, rescission, or another contractual right, and the court may have discretion under Article 234.
As a general rule in bilateral contracts, notice to perform should precede a rescission request, subject to valid statutory exceptions or an express agreement dispensing with notice. The required method of service and cure period must also be followed.
A properly drafted clause may provide for rescission by operation of the agreement without a judgment creating the rescission. However, the triggering breach and procedure must be satisfied, and Article 235 generally preserves the notice requirement unless the parties expressly agreed otherwise.
Yes. Depending on the facts and applicable law, rescission may be refused where the breach has been cured or the unperformed part is minor compared with the obligation as a whole.
Compensation may be awarded where its legal requirements are established, but the loss and its connection with the breach must be proven and calculated. Rescission alone does not establish the amount of damages.
The general principle is restoration of the parties to their pre-contract position, subject to the value of work performed, benefits received, set-off, security, and other consequences of the specific contract. If restoration is impossible, compensation may be relevant.
Higher cost alone is not normally enough to establish force majeure because force majeure is linked to impossibility of performance. Exceptional general circumstances that make performance excessively onerous may engage a different legal framework, including Article 224.
Not necessarily. Article 340 preserves judicial control over agreed compensation in accordance with the statutory criteria, including issues such as partial performance, disproportionality, and contribution to the loss.
The date of the agreement, the date of the relevant event, transitional rules, and any special legislation must be reviewed. The new Civil Transactions Law should not be applied automatically merely because a dispute or court case arose after 1 June 2026.
Not necessarily. An arbitration agreement may survive for the purpose of deciding disputes about termination, breach, damages, and post-termination consequences. Its wording, scope, parties, and validity should be reviewed.
Legal Notice: This article provides general information only and is not a substitute for legal advice on a specific contract. The applicable law, contract date, jurisdiction, deadlines, evidence, special legislation, and the exact wording of the agreement must be reviewed before action is taken.
Content updated: 11 November 2026

Managing Partner
Former Chief Justice of the Federal Supreme Court
Abu Dhabi: 2nd Floor, SJ Tower, 18th Street, Abu Dhabi.
Dubai: Office 1610, 16th Floor, Iris Bay Tower, Business Bay, Al Mustaqbal St.
Mail: [email protected]
Mon – Fri: 8.00am – 18.00pm / Sat & Sunday : Closed